Transmontana, contract year to date. Deductions each obligation has triggered, and what they will cost by year end.
| Obligation | Threshold | October | January to October | Deductions |
|---|---|---|---|---|
| Lane availabilitySchedule 6, 2.1. €1,500 per 0.1 point below 99.0% | at least 99.0% | 99.4% |
| €0 |
| Incident responseSchedule 4, 3.2. €600 per point below 85% | at least 85.0% | 91.3% |
| €0 |
| Category 1 defectsSchedule 5, 4.1. €750 per point below 95% | at least 95.0% | 95.4% |
| €0 |
| Category 2 defectsSchedule 5, 4.2. €400 per point below 90% | at least 90.0% | 91.7% |
| €71 |
| Safety inspectionsSchedule 5, 2.3. €250 per point below 90% | at least 90.0% | 94.5% |
| €0 |
| Emergency phonesSchedule 7, 1.4. €500 per point below 98% | at least 98.0% | 97.9% |
| €1k |
| Traveller informationSchedule 7, 3.1. €400 per minute over 8 minutes | at most 8.0 min | 5.8 min |
| €0 |
Deductions scale with network length and stop at each concession’s annual cap. September’s are notified and open to dispute; October’s are provisional until assessment. The evidence pack has the month-by-month calculation.