02 — Where should management intervene?

6 items need a decision. 2 are high priority and 1 is past its escalation date.

7 escalation rules active
Filter by type
High priorityATT-0412 · A23 Beira Interior

Preventive compliance below target for 3 months

Why it is here: Preventive compliance under 90% for three consecutive months triggers a corporate review.

Compliance
84%
Target 90% · was 91% in July
Overdue PM orders
38
24 on drainage and signage
Contractor Lot 2
61%
of planned volume delivered

Evidence

  • WO-24-18833Culvert clearance km 112, 19 days late
  • WO-24-18901Sign cleaning batch, km 140–152
  • INS-24-0771Principal inspection, drainage defects
  • CTR-L2-09Contractor recovery plan, submitted 14 Oct

Timeline

  1. 29 Sep
    Rule triggered, item opened
  2. 06 Oct
    Escalated to Operations Director
  3. 14 Oct
    Contractor submitted recovery plan

Suggested next step

Approve the contractor recovery plan with a 6-week checkpoint, or reallocate drainage work to the framework contractor.

Ask TRL for a review